IMG_1716.JPG

COMPLETED
2021
 

COMPLETED
2021
 

Phase BU-1B Burlington Reaches Final Completion

-- UPDATE --
January 3, 2022
Phase BU-1B for the Mouse River Enhanced Flood Protection Project steadily progressed through the 2021 construction season and successfully reached final completion in December. The second construction phase for the Burlington portion of flood control had a final construction cost of $8.6M and was completed in 18 months.

The project features 3,400 feet of levee along with a bentonite-cement seepage cutoff which extends approximately 35 feet beneath the levee base. The levee system features an asphalt shared use path along the crest providing for additional recreation opportunities as well as aids in maintenance. The Kittelson Pump Station was also constructed during this phase and will utilize several new sections of storm sewer to control drainage on the interior side of the levee.

Items completed in the fall of 2021 required to reach final completion included final placement of levee fill, installation of storm sewer along Grace Street, Willow Street, and near the Burlington Recreation Complex. Additional pieces which were completed; final topsoil placement, restoration, seeding, and tree plantings gave a finished look to this project phase.


 

Phase BU-1B LIVE CAM

Phase BU-1A & BU-1B City of Burlington

urban flood control

Phase BU-1 is a flood risk management system that encompasses a significant portion of the City of Burlington, North Dakota. Phase BU-1A is the bridge portion of the BU-1 project. These projects are currently at a 100% design level. The project parameters include the north (upstream) section of the system which starts at Park Road near the Canadian Pacific Railroad and extends along the Des Lacs River toward the Des Lacs/Mouse River confluence, from the confluence the MREFPP - Phase BU-1 extends south crossing Colton Avenue, and ultimately encompassing the southern (downstream) section of the City near the Riverwood Subdivision and the Canadian Pacific Railroad.   

Major design features associated with the Phase BU-1 Project include:

  • Approximately 8,830 feet of new dirt levees

  • Seepage cut-off wall integrated with levee alignment

  • Interior stormwater ponding storage areas

  • Levee ramps for access, maintenance, and inspections

  • Kittelson Pump Station and interior drainage improvements

  • Two (2) stoplog road closure structures with floodwall sections at Valley Avenue and Stemen Drive

  • Overbank excavation adjacent to the Mouse River channel extending upstream and downstream of Colton Avenue   

  • Colton Avenue bridge modifications 

  • Temporary levee at Colton Avenue crossing

  • River bank and levee erosion protection 

  • Sanitary, water main, force main, and storm sewer upgrades for pipe networks crossing under the levee within the Project right-of-way

  • Municipal infrastructure modifications and improvements, including sanitary sewer, water main, storm sewer, and street reconstruction

  • City greenway features including bike trail system and open space


 

Phase BU-1 -  City of Burlington, 60% Design Flyover of the Project

Maps depicting the project are included above. The Burlington projects will be constructed in three separate phases with the bridge project substantially completed in 2019, phase BU-1B consisting of the area south of the Colton Avenue Bridge, and the remaining elements to be completed following that. Construction on BU-1B is scheduled to begin in 2020 and will likely take two construction seasons to complete.

Project Photo Gallery