top of page

IN CONSTRUCTION

Phase MI-7: Roosevelt Park and Zoo

CONSTRUCTION UPDATE

April 2025

Construction on Phase MI-7 of the Mouse River Enhanced Flood Protection Plan throughout Roosevelt Park and Zoo has fully ramped up for the 2025 construction season. Both prime general contractors, Wagner Construction and Mattson Construction, have taken advantage of favorable spring weather and have been making progress on nearly all aspects of the project.

Mattson Construction has been working on the interior remodeling of the recently relocated Discovery Barn. Interior renovations include repurposing the former bathrooms into a new outreach area, updating electrical and plumbing, and restoring the exhibit space impacted by the relocation. Exterior site work is ongoing, including sidewalks connecting the Discovery Barn to existing Zoo pathways. Animals used for the Zoo’s outreach program are anticipated to be rehomed to the barn in May. The Discovery Barn is expected to be reopened to the public this summer. A new camel exhibit is also scheduled for construction this summer.

Construction on the new Zoo concessions stand has resumed. Underground utilities have been routed to the building and the concrete flood slab has been poured. Framers are onsite and have begun vertical construction soon to be followed by plumbing, HVAC, and electrical subcontractors. The new concessions stand is anticipated to be open this summer.

Construction of the new Magic City Express Maintenance Building and the new Roosevelt Park restrooms was suspended over the winter months but will resume as conditions allow. The Magic City Express Maintenance Building will be a metal sided wood framed building and will house the model train. The new restroom will be concrete block construction and will be located on the north side of the pickleball courts. Both buildings will be completed this summer.

Wagner Construction has been rapidly moving forward with numerous tasks related to the proposed flood control improvements included in the MI-7E contract. Site clearing, tree removal, and demolition of existing structures through the park and in the zoo for the proposed floodwall and levee corridor are all mostly complete. The four preconsolidation piles that were placed last fall have reached anticipated levels of settlement and have been removed and incorporated into the proposed levee.

Installation of the seepage cutoff wall located beneath the proposed levee and flood wall has begun with the first 200-foot section. This first section will be used as a test to verify the proposed mixture of native soils, cement, bentonite, and water meets specified strengths and permeability. Full production of the seepage cutoff wall is anticipated to resume in early May once test results are available.

The first portion of utility work has also begun. Relocation of a major 27-inch sanitary sewer main that serves a portion of the downtown area started in early April. The first sections of sewer main installed included a directional bore beneath the Mouse River and open cut excavation of dead loop.

Upcoming construction activities include installation of the seepage cutoff wall followed by placement of levee fill in the north end of the park and construction of concrete floodwall through the Zoo. Floodwall construction will continue into 2026. Utility work will continue through the summer with various sections of water, sanitary sewer, and storm sewer throughout the park, Zoo, and adjacent areas.

phase mi-7 Roosevelt Park aerial

VIEW AERIAL FOOTAGE

Visit our YouTube Channel for continued updates of construction progress.

PROJECT OVERVIEW

Phase MI-7 Roosevelt Park and Zoo

urban flood control

The design team continues to work towards 90% plan completion and specifications with a March 1, 2023, date for 90% submittal to the Souris River Joint Board.  The Design Water Surface has been revised based on the proposed alignments, the levee profiles have been adjusted accordingly.

60% of comments received from United States Army Corp Engineers, IEPR, City of Minot, and the SRJB have been addressed.

There is currently a lot of coordination with multiple stakeholders on impacts, utilities and alternate solutions. The team is discussing with Minot Parks impacts to Roosevelt Park and the surrounding area, considering traffic circulation and tree preservation. The Roosevelt Park Zoo Director, Jeff Bullock, on the proposed relocation of the North American Exhibit from the north side of the Mouse River into Roosevelt Park and Master planning has been completed to provide a potential lay out.  We continue working on individual exhibits, structures, and other miscellaneous zoo features. Another larger impacted landmark staple of Roosevelt Park is Magic City Express, a miniature locomotive that travels throughout the park providing a unique view of the whole space. The alternate design of Magic City Express is at 90% design completion with the proposed route being maintained on the dry side of the levee and circling the newly relocated portion of RPZ.

The MI-7 Design team continues coordinating with the City of Minot and several franchise utilities to walk through plans for maintaining service during construction, reroute franchise utilities, and design of municipal utilities through the levee/floodwall system. The team is working on a variety of required permitting with EA, construction permit, and Sovereign Lands permits for both MI-6-Downtown and MI-7-Roosevelt Park and Zoo.

Our whole team continues coordination with the team working on MI-6-Downtown project understanding portions of these two phases will likely be bid as a single project.  Utilities, drainage, levee/floodwall profiles, and alignments have all been coordinated.  The team is working through the development of several construction phase options which would fit within a proposed Phase 1 construction budget and would limit the impacts to operation of Roosevelt Park, RPZoo, and the pool.

mi 7 prelim design.png

Document Downloads For This Project

Phase MI-7 Roosevelt Park and Zoo

urban flood control

The design team continues to work towards 90% plan completion and specifications with a March 1, 2023, date for 90% submittal to the Souris River Joint Board.  The Design Water Surface has been revised based on the proposed alignments, the levee profiles have been adjusted accordingly.

60% of comments received from United States Army Corp Engineers, IEPR, City of Minot, and the SRJB have been addressed.

There is currently a lot of coordination with multiple stakeholders on impacts, utilities and alternate solutions. The team is discussing with Minot Parks impacts to Roosevelt Park and the surrounding area, considering traffic circulation and tree preservation. The Roosevelt Park Zoo Director, Jeff Bullock, on the proposed relocation of the North American Exhibit from the north side of the Mouse River into Roosevelt Park and Master planning has been completed to provide a potential lay out.  We continue working on individual exhibits, structures, and other miscellaneous zoo features. Another larger impacted landmark staple of Roosevelt Park is Magic City Express, a miniature locomotive that travels throughout the park providing a unique view of the whole space. The alternate design of Magic City Express is at 90% design completion with the proposed route being maintained on the dry side of the levee and circling the newly relocated portion of RPZ.

The MI-7 Design team continues coordinating with the City of Minot and several franchise utilities to walk through plans for maintaining service during construction, reroute franchise utilities, and design of municipal utilities through the levee/floodwall system. The team is working on a variety of required permitting with EA, construction permit, and Sovereign Lands permits for both MI-6-Downtown and MI-7-Roosevelt Park and Zoo.

Our whole team continues coordination with the team working on MI-6-Downtown project understanding portions of these two phases will likely be bid as a single project.  Utilities, drainage, levee/floodwall profiles, and alignments have all been coordinated.  The team is working through the development of several construction phase options which would fit within a proposed Phase 1 construction budget and would limit the impacts to operation of Roosevelt Park, RPZoo, and the pool.  
 

bottom of page