Phase MI-2B Souris Valley Golf Course Temporary Greens and Tees

urban flood control

This phase of the project created temporary greens and tees on three holes at the Souris Valley Golf Course. These improvements will provide the golf course with continued playability of all 18 holes throughout the duration of the Napa Valley project, which directly impacts the golf course. These greens and tees were constructed during the 2016 construction season and were available for play in 2017.

As a part of the Napa Valley project, these three holes will be reconfigured and reconstructed. These improvements will be completed during phase 2 which is expected to be completed in 2020.

The golf course will remain open throughout construction.