Fall 2024 Construction Updates on MI-5 Northeast Tieback Levee

  • Nov 11, 2024
  • 1 min read

Construction of Railway Avenue is nearing completion and is scheduled to be open to through traffic starting Friday evening, November 15th.  There will be ongoing work in the boulevards and behind the back of the sidewalk, so please exhibit caution while traveling through the corridor. 

Work completed in this corridor since the roadway was first closed consisted of the following items:

·         2,500 Feet of Concrete Floodwall

·         2,300 Feet of Earthen Embankment

·         4,400 Feet of Roadway Improvements

·         Nearly 53,000 Feet of Underground Utilities were removed and replaced. 

Work on the stormwater pump station is expected to continue through the Winter, the final construction of Phase MI-5 expected next summer. 













 
 
 

Comments


Recent Posts

Phase MI-2 Napa Valley Project by the Numbers

© 2026 SOURIS RIVER JOINT BOARD

Contact Us
Submit your information if you have questions, or would like to share comments or feedback regarding the project.

  • YouTube Channel
  • Facebook - White Circle

Success! Message received.

mi2_infographic_roadway.png
mi2_infographic_riprap.png
mi2_infographic_utilities.png
mi2_infographic_pumpstation.png
mi2_infographic_dirt.png
bottom of page